首页>资讯>石油石化>埃尼启动Coral Sul FLNG设施船体安装工程

埃尼启动Coral Sul FLNG设施船体安装工程

阅读:1465次 日期:2019/07/25

据世界天然气网站7月22日消息 意大利能源巨头埃尼公司已开始在将停泊在莫桑比克近海的Coral Sul浮式液化天然气(FLNG)处理和液化设施的船体安装工程。

埃尼集团周一在一份声明中称,该设施是Coral南部项目的一部分,该项目将从巨大Coral储层中生产4500亿立方米的天然气。

船体预计将于2020年完成,符合计划于2022年开始生产Coral南部项目的进度。

完成后,Coral Sul浮式液化天然气设施的天然气液化能力将达到340万吨/年。该设施将通过20根总重量为9000吨的系泊缆锚定在约2000米的水深处。

Coral Sul浮式液化天然气设施的施工工程始于2018年,目前正在七个运营中心进行。

3月开始建造系泊设施,9月开始建造包含液化天然气储罐和处理设施部分的船体24个模块。上部结构包括12个天然气处理和液化天然气模块以及相应的生活区从去年11月开始建造。

埃尼表示,到2019年底,该项目的总体进度预计将超过60%。

为液化装置提供原料的六口海底油井的钻井和完井活动将于2019年9月开始。这些井的平均深度约为3000米,将在约2000米的水深范围内进行钻探。

Saipem 12000钻机将于2020年底完成这些钻探活动。

吴恒磊 编译自 世界天然气

原文如下:

Eni begins Coral Sul FLNG hull installation works

Italian energy giant Eni has started installation works on the hull of the Coral Sul floating liquefied natural gas (FLNG) treatment and liquefaction unit that will be moored offshore in Mozambique.

The unit is part of the Coral South project, which will put in production 450 billion cubic meters of gas from the giant Coral reservoir, Eni said in a statement on Monday.

The hull is expected to be launched in 2020, in line with the planned production startup of the Coral South project in 2022.

The Coral Sul FLNG facility will have a gas liquefaction capacity of 3.4 million tons per year when completed. The facility will be anchored at a water depth of around 2,000 meters by means of 20 mooring lines that weigh a combined 9,000 tons.

Construction works on the Coral Sul FLNG started in 2018 and are ongoing in seven operational centers.

Construction of the mooring turret began in March; construction of the hull’s 24 modules that contain the LNG storage tanks and sections of the treatment facilities began in September. Construction of the topside, consisting of 12 gas treatment and LNG modules, started last November, along with the living-quarters.

By the end of 2019, the overall progress of the project is expected to exceed 60 percent completion, Eni said.

Drilling and completion activities for the six subsea wells that will feed the liquefaction unit will begin in September 2019. The wells will have an average depth of approximately 3000 meters and will be drilled in about 2000 meters of water depth.

The activities, carried out by the Saipem 12000 drilling rig, will be completed by the end of 2020.

若文章存在版权问题,请与我们联系,我们将在第一时间内删除,谢谢!
上一篇:济南市大力实施两年攻坚行动 确保2020年底前全面解决农村饮水安全问题
下一篇:效率高达98%,比利时厂商推全新设计电机
返回顶部